97889 64456 72312 47532 85224 72311 99738 05314 18822 88877 83701 91188 72106 98803 83485 70762 67561 00923 55229 06479 57972 59061 74949 93171 14807 03728 86417 14924 55271 76483 09709 80826 48003 69756 41326 33857 90179 16007 50123 74390 32549 30315 44217 63317 75601 80709 41762 62320 18455 61834 28274 17965 11564 40730 97515 38882 00045 18375 34435 87730 65633 86354 42635 03181 37624 00288 29224 98754 64198 42645 13159 80277 57942 84214 09885 11406 37363 27238 16160 82824 82750 03902 45252 98749 86602 85405 74120 11069 70749 63642 54482 33973 81058 25338 11638 53184 38067 75862 58160 05931 81160 94118 63131 11678 37627 13358 15577 41533 20376 02073 54475 97260 40548 91470 84971 47067 00960 20371 54295 32383 70544 08125 72446 96640 07075 16165 30869 08344 20223 85830 11652 84248 58240 18720 83640 74865 63798 26432 11368 91553 98930 40390 63732 07578 52004 83379 91665 87295 27594 70342 33614 00445 56766 74846 32119 67664 51801 34739 44392 32414 80290 43295 50949 32938 59188 82226 64963 12065 07486 96473 17151 41690 05059 80565 72757 89563 68610 87113 78719 74762 26213 13426 23716 54025 70952 73308 30338 98371 80443 39662 15506 33308 53719 47268 57523 71539 98084 43052 68615 92226 35372 86296 82533 08533 12606 77475 19780 50069 42332 94775 84463 97795 86712 89454 36026 27730 87899 25252 69813 38682 The surprising results of Habeck's coal emergency plan - BABY-ACE

Power plants go offline again: the surprising result of Habeck's coal emergency plan

  • email

  • Split

  • Further

  • Twitter


  • Press

  • Report a bug

    Did you detect an error?

    Mark the relevant words in the text. With just two clicks you can report the error to the editorial team.

    There is no genetic engineering in the plant.

    But do not worry:
    Genetically modified

    are the

Thursday, March 28, 2024, 11:32

Later this week, the seven lignite blocks that were allowed to operate for longer due to the gas crisis will be removed from the grid. In reality, they were rarely necessary; Therefore, despite the additional capacity, less lignite was used to generate electricity than in previous years.

It was a controversial decision among climate protectors: to reduce the use of gas to generate electricity, in view of the lack of gas supplies from Russia, seven lignite-fired power plants were allowed to operate longer than planned. At the end of this extension, it is clear that the operation of the power plants has hardly caused any additional greenhouse gas emissions.

For this measure, the operator Leag in Lusatia had removed blocks E and F of the Jänschwalde power station from safety status; In the Rhineland, RWE reactivated blocks E and F of the Niederaußem power station and block C of the Neurath power station. In addition, the decommissioning of blocks D and E scheduled for the end of 2022 in Neurath has been postponed.

The extended deadline ends at the end of this week. It was legally limited until March 31, 2024. In view of the relaxed supply situation, the Federal Ministry of Economics (BMWK) has refrained from proposing an extension. The installed capacity of German lignite-fired power plants will therefore be reduced by 3.1 gigawatts to 14.6 gigawatts. Security of supply remains “guaranteed at a high level”, a BMWK spokesperson said upon request. “Due to the significant increase in renewable energy and the stabilization of gas supply, the continuous operation of power plant blocks is neither necessary nor economical.”

Underutilized performance

The Energy Industry Act obliges the federal government to determine the CO₂ emissions caused by the operation of the additional lignite blocks and to submit proposals by the end of June on how to offset them. There are currently no figures on the climate impact of the revival, BMWK explained upon request.

However, data on electricity generation in Germany, presented among others on the website energy-charts.info, already suggest that the impact of the additional power plant blocks on the climate balance was small. The maximum installed lignite capacity was almost never fully utilized in the last two winters; The additional blocks often replaced other lignite power plants and not gas or coal power plants, which emit less CO₂ per kilowatt hour of electricity produced.

FOCUS online Earth is dedicated to the climate crisis and how to overcome it.

Focused on facts. Well founded. Constructive.
Every week as a newsletter.

*Fields marked with an * are required

Data on the use of power plants also suggests that they were rarely needed: in the two Niederaußem blocks, this represented only a good 20 percent in 2023. In Neurath it was a good 30 percent, in Jänschwalde around 35 percent. At the same time, the utilization of the remaining blocks in these locations decreased significantly compared to most previous years, so that overall, despite the additional production, less electricity was produced from lignite in the affected locations than in previous years.

Controversial emergency plans

With the closure of the seven power plant blocks, Germany returns to the agreed timetable for phasing out coal. In 2020, a phase-out until 2038 was enshrined in law; An agreement was concluded for the Rhineland in 2022 that brings it forward to 2030; This has not yet been possible for Lusatia. However, experts expect that coal-fired power generation will also become unprofitable in the early 2030s due to the rising price of CO₂. To ensure security of supply, gas-fired power plants with hydrogen capacity are planned for some of the current coal-fired power plants; RWE aims for a capacity of at least three gigawatts in its facilities.

Get free access for 30 days to more exclusive insights from Table.Media Professional Briefings – the crucial information for decision makers in business, science, politics, management and NGOs.

The basis for the reactivation of coal power plants was the declaration of the alert level in the gas emergency plan in the summer of 2022 due to the cessation of gas supplies from Russia. Although the Federal Ministry of Economy justifies the closure of coal-fired power plants with the “stabilization of gas supply”, the alert level should be maintained. This is probably because this is the prerequisite for accelerating the construction of LNG terminals on the German coast. And so far the federal government has stuck to these plans, despite protests from environmentalists and several studies that doubt their necessity.

+++ Don't miss more climate news: subscribe to our WhatsApp channel +++